Abu Dhabi National Exhibition Centre (ADNEC) hosts ADIPEC, IDEX, ADIHEX and other major regional events. If you are building a custom stand at ADNEC, your design will need to work within hall-specific height allowances, floor loading capacities, walling and sightline rules, and fire-safety certification requirements — and your drawings will normally need review and approval before build-up begins.
This guide sets out what we have learned building at ADNEC, so you know what to plan for before committing to a design.
Important: verify the current event manual
Please read before relying on this guide. This independent guide is based on Maple Expo’s practical project experience. This Guide is provided for general information only. It is not issued, endorsed or approved by ADNEC Group or any event organiser.
Requirements vary by event, hall, stand location and project type, and may change without notice. Before approving a design, placing orders or committing to expenditure, consult the current official exhibitor manual and obtain confirmation from the relevant organiser or venue team.
The information provided on this page is based on Maple Expo’s practical experience in exhibition stand design, production, venue coordination, and project delivery. Requirements, procedures, pricing, timelines, and venue rules may change and can vary by event, organiser, venue, and project. While we aim to keep the information accurate and up to date, Maple Expo does not guarantee that every detail will apply to every situation. Always confirm current requirements directly with the relevant organiser, venue, or official event documentation before making any decision or commitment.
ADNEC Stand Height Allowances by Hall
Height allowances at ADNEC are set per hall rather than venue-wide, which catches out exhibitors who design a stand before knowing where they will be located. The pattern below reflects our own build experience. It is indicative only — allowances differ by event and are revised between editions.
| Location | Single-level (indicative) | Double-decker (indicative) |
|---|---|---|
| Main exhibition halls | Around 4 m | Commonly permitted, greater height |
| Atrium | Similar to main halls; less in low-ceiling areas | Commonly permitted |
| Atrium Link | Substantially lower — around 2.5 m | Generally not permitted |
| Concourse | Lower than main halls — around 3 m | Generally not permitted |
| Ancillary halls | Around 4 m | Generally not permitted |
Practical consequence: a design which works in a main hall may be unbuildable in the Atrium Link or Concourse, where the ceiling is considerably lower. Confirming your hall allocation and its specific allowance before design work begins is one common way to avoid a costly redesign.
Double-Decker Stands at ADNEC
Double-decker stands are used at ADNEC, subject to conditions that surprise many first-time exhibitors:
- Eligibility is linked to stand size. On projects we have delivered, approximately 36 sqm has been used as a threshold, though this must be confirmed for each event.
- Smaller stands below that size have in our experience been considered case by case by the show operations team, rather than ruled out automatically.
- Double-deck builds are generally not permitted in lower-ceiling areas such as the Concourse and Atrium Link.
- Structural calculations are normally required and reviewed by the venue’s health and safety team alongside your stand drawings.
A structural review fee typically applies to double-deck and complex stands. The amount varies by event and by drawing complexity, so treat it as a separate budget line rather than assuming it sits inside your contractor’s quote, and ask your contractor to confirm the current figure for your show.
Floor Loading
Floor loading is the constraint that matters most if you are displaying machinery, vehicles or heavy equipment — common at ADIPEC and IDEX. Capacity differs substantially between halls, and by more than most exhibitors expect.
| Location | Relative capacity (indicative) |
|---|---|
| Main exhibition halls | Highest — generally suitable for vehicles and heavy machinery |
| Concourse | Materially lower than main halls; forklift access restricted |
| Ancillary halls | Lowest — check carefully before planning heavy exhibits |
Heavy items generally need a uniformly distributed load, and spreader plates are normally required and supplied by the exhibitor. In lower-capacity halls, large or heavy items typically require advance approval from the show operations team. Forklift access is restricted in some areas. If your exhibit is heavy, raise it with your contractor and organiser early rather than discovering the constraint during build-up.
Walling and Sightlines
ADNEC events apply sightline rules so that neighbouring stands remain visible from the aisle.
- Limits typically apply to solid walling on open aisle-facing sides.
- Back and side walls are generally required where stands adjoin a neighbour, except island/free-standing stands.
- The rear surface of walls taller than an adjacent stand normally needs to be finished and painted.
Stand Roofs in Overlooked Areas
Some event manuals require stands visible from upper levels — such as the Concourse, Atrium and Link areas — to have a properly finished and dressed roof. Confirm whether this applies to your hall and event, and if so include the top view in your 3D renders and structural drawings.
Fire Safety and Materials
Stand materials must comply with the fire-safety and certification requirements stated in the applicable event manual. In practice this usually means fire-retardant certification for potentially flammable materials, and decorative textiles meeting flammability or surface spread of flame standards.
Security Deposits
Some ADNEC events require a refundable security deposit for space-only stands. Where one applies, the amount generally scales with stand size, and national pavilions are usually assessed separately. Check the event manual for the amount, payment deadline and refund conditions for your show.
Where a deposit applies, the organiser or venue may make deductions where permitted by the applicable event terms — typically for non-compliance such as unfinished wall rears, uncovered stand tops in overlooked areas, or waste left on site.
Waste, Paint and Site Rules
- Contractors are generally responsible for removing their own build-up and breakdown waste.
- Paint cans and hazardous chemicals must not be placed in general skips; a per-item charge may apply.
- Skips are normally hired through the venue, with external waste suppliers typically not permitted on site.
- Stand space is normally expected to be vacated with adhesive tape, paint and similar traces removed.
- Lighting accessories generally must sit within your allocated space and not protrude into aisles.
- Crew numbers on stand are also typically capped relative to floor area.
Water, Waste Services & Build-Up Access
Water and Waste Services
Water and waste connections are generally available only from designated floor service pits in specific hall locations, and not from electrical service trenches. Some areas cannot be serviced at all.
Supply is normally suitable for liquid water disposal only — foodstuffs, oils, dyes and chemicals must not be put through it. Supply pipes generally cannot cross gangways or emergency routes, and exhibitors are usually responsible for dressing visible pipework.
Build-Up and Access
ADNEC build-up runs on an allocated schedule, and access arrangements differ between space-only exhibitors and shell scheme stands. Space-only contractors are typically given extended access windows across several days ahead of the show, with halls opening in a staged sequence.
Vehicles and heavy machinery usually need to enter the halls before general build-up begins, because stands are built around them. Scheduling is managed and enforced.
The Stand Approval Process
| Step | What happens | Who does it |
|---|---|---|
| 1. Design | 3D concept and technical drawings produced | Your contractor |
| 2. Submission | Stand design and contractor documentation filed | Your contractor |
| 3. Structural review | Calculations reviewed for complex/double-deck stands | Venue H&S team |
| 4. Approval | Design signed off before build-up | Venue and organiser |
| 5. Deposit | Paid ahead of the published deadline, where applicable | Exhibitor |
| 6. Build-up | Construction within the allocated access window | Your contractor |
| 7. Breakdown | Full removal including waste | Your contractor |
Common Mistakes at ADNEC Shows
- Designing before knowing the hall. A design sized for a main hall may not fit a lower-ceiling area such as the Atrium Link.
- Assuming a double-deck is available. Eligibility is tied to stand size and location, and several areas do not permit it.
- Overlooking floor loading in ancillary halls, where capacity is materially lower than the main halls.
- Leaving wall rears unfinished where they exceed a neighbour’s height, which may lead to a charge or deposit deduction.
- Forgetting the stand top in areas overlooked from upper levels, where a finished roof may be required.
- Budgeting no allowance for structural review fees or a security deposit.
- Disposing of paint or chemicals in venue skips, which may attract a per-item charge.
Choosing a Contractor for an ADNEC Show
Contractor eligibility and registration requirements may vary by event. Confirm the applicable requirements with your organiser before appointing a contractor, as event registration, permits, site inductions and organiser approval may all apply in addition to licensing and insurance.
Useful questions include: have you built in this hall before, do you prepare and submit structural drawings yourselves, is fabrication in-house or subcontracted, and does the quote include dismantling and waste removal?
Maple Expo works at ADNEC and DWTC, fabricates stands in our own Dubai workshop, and coordinates the preparation and submission of drawings for approval on behalf of our clients.
Exhibiting at ADNEC — Frequently Asked Questions
Quick answers to the most common planning and compliance questions.
Height allowances are set per hall rather than venue-wide. Based on our project experience, main exhibition halls have typically allowed around 4 m for single-level stands, while lower-ceiling areas such as the Concourse and Atrium Link are considerably more restricted. These figures are indicative only — confirm the allowance for your hall and event with your organiser before designing.
Eligibility is linked to stand size. On projects we have delivered, approximately 36 sqm has been used as a threshold, with smaller stands considered case by case by the show operations team. This must be confirmed for each event. Double-deck builds are generally not permitted in lower-ceiling areas.
A structural review fee typically applies to double-deck and complex stands requiring structural calculations. The amount varies by event and by drawing complexity, so ask your contractor to confirm the current figure for your show and budget it as a separate line item.
Capacity varies significantly by hall, with main exhibition halls carrying substantially more than the Concourse or ancillary halls. Spreader plates are normally required for heavy loads and supplied by the exhibitor. Obtain the exact figure for your hall from your organiser before planning heavy exhibits.
Some events require a refundable security deposit for space-only stands. Where one applies, the amount generally scales with stand size. Check the event manual for the amount, deadline and refund conditions for your show.
Sightline rules are generally intended to protect visibility between neighbouring stands, which typically means limits on how much of an open side facing an aisle may be solid walling. Where a wall is taller than the adjacent stand, the rear surface normally needs to be finished and painted. Confirm the specific requirements in your event manual.
Some event manuals require stands in areas visible from upper levels to have a properly finished roof. Confirm whether this applies to your hall and event. Where it does, include the top view in your 3D renders and structural drawings.
Stand materials must comply with the fire-safety and certification requirements stated in the applicable event manual. This usually means fire-retardant certification for potentially flammable materials and decorative textiles meeting flammability standards. Specify compliant materials at design stage.
Generally only in halls with designated floor service pits, and not from electrical trenches. Some areas cannot be serviced. Confirm availability for your specific stand location before designing anything requiring water.
Contractor eligibility and registration requirements may vary by event. Event registration, permits, site inductions and organiser approval may apply in addition to licensing and insurance. Confirm the applicable requirements with your organiser before appointing a contractor.
Before You Rely on These Figures
The guidance in this article reflects Maple Expo’s project experience. ADNEC applies different requirements to different halls, organisers set additional conditions for each event, and both change between editions. Height allowances, loading capacities, review fees and deposits should be treated as orientation rather than as current specification.
Before committing to a stand design, confirm the requirements for your show against the official exhibitor manual issued by your organiser, or ask your contractor to check on your behalf. For each project, Maple Expo reviews the applicable event manual and coordinates confirmation of relevant requirements before drawings are submitted.
The information provided on this page is based on Maple Expo’s practical experience in exhibition stand design, production, venue coordination, and project delivery. Requirements, procedures, pricing, timelines, and venue rules may change and can vary by event, organiser, venue, and project. While we aim to keep the information accurate and up to date, Maple Expo does not guarantee that every detail will apply to every situation. Always confirm current requirements directly with the relevant organiser, venue, or official event documentation before making any decision or commitment.
Planning a Stand at ADNEC?
Maple Expo coordinates stand design, structural drawings, approval submissions, fabrication and installation for ADNEC shows including ADIPEC. As an established exhibition stand contractor in Dubai, we help clients reduce the risk of avoidable non-compliance charges and deposit deductions by getting the compliance detail right before build-up.
Send your show name, hall and stand size.